Zimapan waste disposal, Hidalgo, Mexico

Description

Desde 1994, cuando la secretaría del Medio Ambiente y Recursos Naturales (Semarnat), autorizó a la empresa española Abengoa para construir la planta de reciclado y el confinamiento de desechos industriales más grande de México en este municipio del estado de Hidalgo en la Sierra Gorda, comenzó a gestarse la tensión. Se pretendía construir en el ejido Cuauhtémoc, en una superficie de casi 133 hectáreas en este municipio, ubicado a nueve kilómetros de la cabecera municipal de Zimapan. Es una zona de comunidades indígenas otomíes (ñahñuh).

See more...
Basic Data
NameZimapan waste disposal, Hidalgo, Mexico
CountryMexico
ProvinceHidalgo
SiteEjido Cuauhtémoc, Zimapan
Accuracy of LocationMEDIUM regional level
Source of Conflict
Type of Conflict (1st level)Waste Management
Type of Conflict (2nd level)Landfills, toxic waste treatment, uncontrolled dump sites
Specific CommoditiesDomestic municipal waste
Industrial waste
Project Details and Actors
Project DetailsConfinamiento, ubicado en el ejido Cuauhtémoc, en la comunidad Botiña, en Zimapán. Hidalgo. La planta ocupa 133 hectáreas, por las cuales Befesa (que representa a Abengoa) paga una renta de 10 mil pesos mensuales. El vertedero, con capacidad de 600 mil toneladas de desechos peligrosos, abarca una superficie de 24 hectáreas, donde se asienta uno de seis vasos contenedores de 800 metros de diámetro por 160 de profundidad.

El líder de Todos Somos Zimapán, Williams Trejo, afirmó en 2010 que luego de cinco años de plantones y enfrentamientos con policías estatales y federales, los ciudadanos vencieron. "La empresa se instaló en Hidalgo mediante engaños, pues primero aseguró que pretendía instalar una planta recicladora de desechos industriales y luego resultó que era un vertedero de residuos altamente tóxicos".
Project Area (in hectares)133
Level of Investment (in USD)15,000,000
Type of PopulationSemi-urban
Start Date2004
Company Names or State EnterprisesABENGOA S.A. from Spain
Relevant government actorsSemarnat, Procuraduría Federal de Protección al Ambiente (Profepa)
Environmental justice organisations and other supportersTodos somos Zimapan, El Barzon, Ecologistas en Acción
The Conflict and the Mobilization
Intensity of Conflict (at highest level)HIGH (widespread, mass mobilization, violence, arrests, etc...)
When did the mobilization beginIn REACTION to the implementation (during construction or operation)
Groups MobilizingFarmers
Indigenous groups or traditional communities
Local ejos
Local government/political parties
Neighbours/citizens/communities
Social movements
Ethnically/racially discriminated groups
Religious groups
Forms of MobilizationCreation of alternative reports/knowledge
Development of a network/collective action
Involvement of national and international NGOs
Lawsuits, court cases, judicial activism
Media based activism/alternative media
Objections to the EIA
Official complaint letters and petitions
Street protest/marches
Impacts
Environmental ImpactsPotential: Soil contamination, Waste overflow, Surface water pollution / Decreasing water (physico-chemical, biological) quality, Groundwater pollution or depletion, Large-scale disturbance of hydro and geological systems
Health ImpactsVisible: Exposure to unknown or uncertain complex risks (radiation, etc…)
Potential: Other environmental related diseases
Socio-economic ImpactsVisible: Militarization and increased police presence, Violations of human rights
Outcome
Project StatusStopped
Pathways for conflict outcome / responseCompensation
Violent targeting of activists
Project cancelled
Do you consider this as a success?Yes
Why? Explain briefly.The project was cancelled because of local resistance, however Abengoa got money from Mexico in compensation in the arbitration tribunal CIADI at the World Bank, Washington DC
Sources and Materials
References

Crítica de Ecologistas en Acción (España) por el arbitraje en el CIADI - argumentan que México no debe pagar a Abengoa
[click to view]

Ana Liria Perez, 2011, narración del caso hasta el arbitraje
[click to view]

Proyecto Zimapan cancelado, 2010. Carlos Camacho, La Jornada, 23 de julio de 2010
[click to view]

Links

El inicio del conflicto desde 2004, narrado en 2008, "Zimapán crece el descontento por planta de residuos peligrosos" , por Sergio Islas

Sergio Islas
[click to view]

Descripción detallada del proyecto, 2008
[click to view]

Meta Information
Contributorjoan martinez alier
Last update01/07/2014
Comments