Embalse La Punilla, Ñuble, Chile

Forced displacement and destruction of homes of neighbors for acquisition of land with no resettlement plan, in the name of allegedly improvement in agriculture and water provision for farmers


Description:

En la región del Ñuble, la comunidad y organizaciones sociales están en pie de guerra contra la construcción del Embalse la Punilla, proyecto concesionado por Empresa Astaldi y financiado interamente por el Ministerio de Obras Públicas. La iniciativa tiene supuestamente por objetivo garantizar el riego para alrededor de 70 mil hectáreas pero también instalar componente hidroeléctrica de 94 MW. Además otra central hidroeléctrica, llamada HidroÑuble, explotaría el caudal del río aguas abajo, cerca del poblado de San Fabían (ver ficha de conflicto en el EJAtlas).

See more
Basic Data
Name of conflict:Embalse La Punilla, Ñuble, Chile
Country:Chile
State or province:Región de Ñuble
(municipality or city/town)San Fabián de Alico
Accuracy of locationMEDIUM (Regional level)
Source of Conflict
Type of conflict: 1st level:Water Management
Type of conflict: 2nd level :Land acquisition conflicts
Dams and water distribution conflicts
Specific commodities:Land
Electricity
Water
Project Details and Actors
Project details:

Según sus promotores, el embalse La Punilla "se construirá 30 kilómetros aguas arriba de San Fabián de Alico y a 3 kilómetros de la confluencia de los ríos Ñuble y Los Sauces, en la Región del Biobío. Beneficiará a 5.000 agricultores y 60.000 hectáreas de las comunas de San Carlos, Chillán, Ñiquén, San Nicolás, Coihueco y San Fabián de Alico, y a otras 10.000 hectáreas adicionales de predios que hoy no cuentan con derechos de agua.

See more
Project area:2,200 (de los cuales 1,200 de bosque nativo)
Level of Investment:397,000,000 [1]
Type of populationRural
Company names or state enterprises:Astaldi from Italy - Constructora
Relevant government actors:Ministerio de Obras Públicas

Gobierno de Chile

Consejo de Ministros de la Comisión Nacional de Riego
Environmental justice organizations (and other supporters) and their websites, if available:Nuble se Hunde

Ñuble Libre
Conflict and Mobilization
IntensityMEDIUM (street protests, visible mobilization)
Reaction stagePREVENTIVE resistance (precautionary phase)
Groups mobilizing:Farmers
Neighbours/citizens/communities
Pastoralists
Social movements
Forms of mobilization:Media based activism/alternative media
Objections to the EIA
Official complaint letters and petitions
Impacts of the project
Environmental ImpactsVisible: Biodiversity loss (wildlife, agro-diversity), Soil contamination, Deforestation and loss of vegetation cover
Potential: Floods (river, coastal, mudflow), Food insecurity (crop damage), Loss of landscape/aesthetic degradation, Surface water pollution / Decreasing water (physico-chemical, biological) quality, Groundwater pollution or depletion, Large-scale disturbance of hydro and geological systems
Health ImpactsVisible: Mental problems including stress, depression and suicide
Potential: Malnutrition
Other Health impactsMental stress due to forced destruction of homes. Forced displacement makes it impossible to properly take care of animals and of their yearly reproduction, which jeopardizes sources of livelihood and basic food of displaced families.
Socio-economical ImpactsVisible: displacement, Increase in violence and crime, Lack of work security, labour absenteeism, firings, unemployment, Loss of livelihood, Loss of traditional knowledge/practices/cultures, Militarization and increased police presence, Violations of human rights, Land dispossession, Loss of landscape/sense of place
Potential: Increase in Corruption/Co-optation of different actors, Social problems (alcoholism, prostitution, etc..)
Outcome
Project StatusPlanned (decision to go ahead eg EIA undertaken, etc)
Conflict outcome / response:Criminalization of activists
Migration/displacement
Repression
Do you consider this an environmental justice success? Was environmental justice served?:No
Briefly explain:Displaced families still live in a temporary shelter after evacuation from their homes, with very precarious conditions for their livelihoods, compensation has not even been granted, criminalization of at least seven families continues.
Sources and Materials
Links to general newspaper articles, blogs or other websites

Revisarán reubicación de familias de San Fabián por embalse Punilla
[click to view]

[3] COMUNIDADES DE SAN FABIÁN DE ALICO LUCHAN POR PRESERVAR EL RÍO ÑUBLE

ESCRITO POR MICHAEL LIEBERHERR PACHECO EL 2 ABRIL 2018
[click to view]

[1] Redagricola - Febrero 2017 | Embalse Punilla: la esperada obra que transformará a Ñuble
[click to view]

[4] radiojgm.uchile

EMBALSE PUNILLA: EMPRESA ASTALDI Y FUERZAS ESPECIALES COMIENZAN DESALOJOS

ESCRITO POR DIEGO ORTIZ FUENTES EL 23 NOVIEMBRE 2018
[click to view]

[5] No Mientan MÁS sobre El PUNILLA

Post on: 7 noviembre, 2018
[click to view]

[7] Cooperativa Regiones - Autoridades realizan visita técnica a zona donde se pretende emplazar el embalse Chillán

Publicado: Miércoles, 24 de Abril de 2019 a las 17:18hrs. Autor: Cooperativa.cl
[click to view]

[8] Tribunal Ambiental de Valdivia ordena suspender desalojos del proyecto embalse Punilla
[click to view]

[2] Radiojgm UChile - 2018

ÑUBLE SE HUNDE POR EMBALSE LA PUNILLA: “ES INACEPTABLE LA CONSTRUCCIÓN DE ESTE TIPO DE PROYECTOS”
[click to view]

Cooperativa.cl - Nuevas expropiaciones se desarrollan en terrenos fiscales del proyecto Embalse Punilla

Publicado: Jueves, 14 de Marzo de 2019
[click to view]

Related media links to videos, campaigns, social network

Campamento desalojados por Embalse Punilla: "lo que la empresa y el MOP ofrecen es una burla"
[click to view]

Embalse Punilla "Todo el proceso está podrido" Hay que replantearlo
[click to view]

Other documents

Fuente: https://www.futurorenovable.cl/no-mientan-mas-sobre-el-punilla/
[click to view]